Project

Wastewater treatment plant aeration system replacement and new garage

Customer :

CITY OF CHAMBLY

Services provided :

  • Construction management
  • Project managemen
  • Subcontractor management
  • Testing, adjustment

Disciplines :

  • Process Mechanics
  • Civil Engineering
  • Building and formwork
  • Plumbing
  • Electricity
  • Ventilation - air conditioning

Project description

The turnkey project consists of :

  • Replace pond aeration system, including turbo air blowers, pond aeration lines and ferric sulfate dosing
  • Pre-treatment replacement including two fine screens
  • Replacing the storage tank
  • Addition of a bypass line
  • Building a detached garage
  • Redevelopment and complete renovation of offices inside the wastewater treatment plant

Project features

  • Work beside a body of water
  • Work in wetlands can only be carried out between 15 June and 15 September
  • Temporary works in a watercourse,
  • Presence of trees to be protected
  • Keeping the plant in operation during the works
  • Complete start-up of the treatment process

Location

2460 BOULEVARD INDUSTRIEL, CHAMBLY(QC) J3L 4V2

Value

$12.2M

Year of completion

2023 - 2024

Whatever the scope of your project, CWA executes the work to meet our customers' needs in the fastest, most cost-effective way, always with quality and safety in mind.

The diversified service offerings of our company and our divisions cover the following areas:

  • Construction
  • Equipment repair and maintenance
  • Management and operations

Contact us

Name(Required)
Address
Service type (optional)

Privacy Policy

2024 CWA mécanique inc. | All rights reserved | Site by DevBuddy