Project description

The project involved the construction of a new wastewater treatment plant for the city of Terrebonne.

Project features

The plant consisted of :

  • Construction of three (3) aeration basins; Pre-treatment: 2 fine screens and a grit chamber for a peak flow of 2,200 l/s (each)
  • Aeration: 4 x 200hp turbo blowers (each), 3 aeration tanks c/a fine bubble diffusers and agitators
  • Decantation: 3 secondary decanters, 141ft diameter (each)
  • Thickening: 2 rotary drums capable of processing 1,000 kg/h of dry matter,
  • Dehydration: 2 centrifuges capable of processing 1,000 kg/h of dry matter,
  • Disinfection: 2 UV ramps, peak flow 2025: 88,600m3/d (each),
  • Odour treatment: packed scrubber and biofilter type odour treatment system, flow rate 49,900 m3/h.

Location

BOULEVARD LA PINIÈRE - TERREBONNE (QC) G6V 7M5

Value

$19.8M

Year of completion

2021 à 2024

Whatever the scope of your project, CWA executes the work to meet our customers' needs in the fastest, most cost-effective way, always with quality and safety in mind.

The diversified service offerings of our company and our divisions cover the following areas:

  • Construction
  • Equipment repair and maintenance
  • Management and operations

Contact us

Name(Required)
Address
Service type (optional)

Privacy Policy

2024 CWA mécanique inc. | All rights reserved | Site by DevBuddy